Rogow railway rebuilt!

by

rogow-rebuilt-1

The last missing piece restored. Photo FPKW.

(Click to see the full track repairs photo gallery).

Over the June long weekend, 30 May to 2 June, FPKW volunteers repaired the last missing section of track on the 49km line from Rogow to Biala Rawska. Works draisine Wmc-009 , pictured above, became the first rail vehicle to reach the end of the line since autumn 2011.

rogow-rebuilt-2

Work begins. New sleepers being laid. Photo FPKW.

The final missing link on the route was a length of stolen rail at km 33.7 near Konopnica. As the sleeper fixings had also been stolen along with the rail, this required completely new sleepers.

rogow-rebuilt-3

Lifting the first rail into place. Photo FPKW.

The repair was only possible thanks to donations from Rawa Mazowiecka district council, PKP PLK, and the National Sugar Company, as well as the many individual donors to FPKW, including those Behind the Water Tower readers who gave money through FPKW’s PayPal donation facility during our campaign to help restore the railway. Thank you to all.

More:

Advertisements

2 Responses to “Rogow railway rebuilt!”

  1. nanstallon Says:

    Good news. Will there be a public service over the whole line?

  2. Ed Beale Says:

    Although the running line is now complete, there is still some work to do before passenger trains can resume, and to this end FPKW are still seeking donations or practical volunteering help (anyone interested should email wolontariat [at] kolejrogowska.pl). They hope to run the first passenger train later this summer.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s